Information management under BS EN ISO 19650-2: A cross-case analysis of implementation conditions in UK construction projects

DOI:10.36680/j.itcon.2026.057
submitted:May 2026
published:November 2026
editor(s):Bosché F
authors:Nicoleta Panagiotidou
University College London, United Kingdom
https://orcid.org/0000-0003-2103-4579
nicoleta.panagiotidou.18@ucl.ac.uk

Michael Pitt, Director of Teaching and Learning
University College London, United Kingdom
https://orcid.org/0000-0002-7643-6113
michael.pitt@ucl.ac.uk

Qiuchen Lu, Associate Professor
University College London, United Kingdom
https://orcid.org/0000-0001-8687-0901
qiuchen.lu@ucl.ac.uk

Sarah Davidson
University of Nottingham, United Kingdom
https://orcid.org/0000-0003-2335-5552
sarah.Davidson@nottingham.ac.uk
summary:Information management (IM) under BS EN ISO 19650-2 has become central to digital transformation in the UK construction industry. Despite its structured framework, implementation in practice remains inconsistent, with organisations interpreting and applying the standard in divergent ways. Existing research has focused on organisational and technological adoption, with limited attention to how IM is enacted within project delivery structures. In particular, the interaction between procurement routes, appointment arrangements, IM resources and Common Data Environment (CDE) practices remains underexplored. This study addresses this gap through a multiple embedded case study of four UK projects procured through Design–Bid–Build and Design and Build routes. Document analysis, interviews and clause-level assessment were used to examine how IM is configured and enacted across delivery and appointment structures, focusing on IM resources and CDE workflows at the lead appointed party level. Cross-case synthesis identified structural and operational conditions combined within four case-derived implementation configurations: fragmented early-stage, integrated delivery, centralised coordination and transitional governance. Variations in governance continuity and stability, coordination authority, appointment sequencing, IM resource formalisation and integration, IM structuring control, and CDE workflow structuring were associated with differences in how IM processes were organised, coordinated and controlled across the cases. The study provides a UK-based cross-case empirical analysis of BS EN ISO 19650-2, positioning implementation as a condition-dependent socio-technical process characterised by the interaction of structural and operational conditions rather than a uniform procedural model. The findings highlight the importance of alignment among procurement and appointment structures, IM resource integration and CDE workflows for consistent IM implementation.
keywords:BS EN ISO 19650-2, information management, BIM, construction procurement, common data environment
full text: (PDF file, 2.688 MB)
citation:Panagiotidou, N., Pitt, M., Lu, Q., & Davidson, S. (2026). Information management under BS EN ISO 19650-2: A cross-case analysis of implementation conditions in UK construction projects. Journal of Information Technology in Construction (ITcon), 31, 1396-1433. https://doi.org/10.36680/j.itcon.2026.057